July 16-22, 2000

THIS WEEK'S WORK

Full Interstate Closures

July 17-20, 10 p.m. - 6 a.m., northbound I-15 from 11800 South to 600 North

July 17-20, 10 p.m. -6 a.m., southbound I-15 from 600 South to 7200 South

July 17-21, 10 p.m. - 6 a.m., southbound I-15 to I-80 eastbound ramp

July 21, 10 p.m. - 8 a.m., northbound I-15 from 11800 South to 600 North

July 21, 10 p.m. - 8 a.m., southbound I-15 from 600 South to 7200 South

July 22, 8 p.m.- 8 a.m., northbound I-15 from 11800 and 4500 South

Ramp Closures

There are no temporary ramp closures this week

Street Closures

July 17, 8:30 a.m. - 3:30 p.m., 6400 South beneath I-15

July 17-19, 10 p.m.- 6 a.m., North Temple beneath I-15

July 17-21, 9 a.m.-3 p.m., 1000 West between 200 and 300 South

July 17-21, 10 p.m.- 6 a.m., 5900 South beneath I-15

July 17-21, 9 a.m.-3 p.m., 300 North beneath I-15

July 18-20, 10 p.m.- 6 a.m., 10600 South between AutoMall Drive and Jordan Gateway intersection

July 21, 10 p.m.- 8 a.m., 5900 South beneath I-15

July 21, 8 p.m.-6 a.m., 400 South between 400 and 900 West

July 21-23, 9 a.m.-3-p.m., 700 West between 800 and 850 South

Openings

July 17, 4 p.m., eastbound I-80 to northbound I-15 with access to 600 North