LEHI — The Utah Department of Transportation will repave State Street from 1100 West in Lehi to 800 North in Orem. Traffic will be reduced to one lane in each direction between 9 p.m. and 6 a.m., Monday through Saturday.
The project, which will continue through Aug. 6, is divided into five sections:
Lehi, 1100 West to Lehi Main Street (U-73).
Lehi's Main Street to American Fork's 700 East.
View Comments
American Fork's 700 East to Pleasant Grove's 100 East (U-146).
Pleasant Grove's 100 East to Lindon's Center Street.
Lindon's Center Street to Orem's 800 North.
Work will begin in Lehi and move south. Crews will work on one side of the road at a time.