The Navy announced Wednesday it will not renew its contract with Hill Air Force Base for the inspection and repair of F/A-18 fighter jets.

The project employs 150 workers at Hill and had the potential of bringing in $61 million.Hill won the contract in August 1993 in competitive bidding with private and military competitors. The Navy had an option to renew the contract on a yearly basis.

"We're disappointed - I'm personally disappointed," said Col. Kevin Sullivan, director of the Aircraft Directorate in Hill's Ogden Air Logistics Center. "We had received no indication from the Navy that they had problems with the planes."

Navy officials have indicated that Hill lost the contract because delivery of the repaired planes has been late and because of budget overruns. But Hill absorbed the extra costs, and officials say the delays made little difference to the Navy at the time.

Many at Hill believe the Navy is just making excuses to take work from Hill and put it back in the Navy's own aviation depot on San Diego's North Island so it can employ its own workers.

"I think their objections are somewhat frivolous," said Utah Rep. Jim Hansen, whose congressional district includes Hill. "I think they're getting into a cross the t's and dot the i's kind of thing . . . The Navy is very jealous of its turf."

No one at the Navy has said the aircraft work itself was anything but top notch, said Ogden ALC Commander Maj. Gen. Pat Condon, and Sullivan agreed.

"The feedback we received from individual unit customers was very good," he said.

Sullivan added that many of the delay problems were the fault of the Navy. Hill often had to stop work to wait for Navy overseers to come in and approve maintenance projects that Hill recommended, and workers spent a lot of time waiting for parts to come in from the Navy.

View Comments

"We did not anticipate the magnitude of the administration of the oversight process," Sullivan said, "(and) there were occasions very clearly where we had delays because of parts problems."

Hansen has requested the Congressional General Accounting Office review the numbers the Navy used in its decision, many of which look suspicious to him. He cites, for example, an apparent discrepancy between what Hill said it was charging for each hour of labor, $61, and what the Navy said, $81.

"We're a little concerned that some of the figures the Navy came up with are a little bit fictitious," Hansen said.

Hill has completed work on eight fighters and has 28 to complete in the initial contract, which it will finish by April.

Join the Conversation
Looking for comments?
Find comments in their new home! Click the buttons at the top or within the article to view them — or use the button below for quick access.