This tentative schedule for construction of the 2.5-mile University TRAX light-rail line is based on completion prior to the 2002 Winter Games. UTA hopes to have the line operational by Nov. 29, 2001.

If delays occur or substantial progress is not made for any reason, the Utah Transit Authority plans to postpone completion of the project in August 2001.

UTA would then temporarily repave the streets for normal use during the Olympics, and then resume construction following the Games with completion set for November 2002.

University TRAX construction schedule

Main Street-400 East:

Sept. 2000-Jan. 2001 — utility relocation.

Feb.-May 2001 — construction of pavement, curb, gutter and sidewalks.

June-Oct. 2001 — pavement resurfacing.

April-Oct. 2001 — track installation, operating systems.

400 East-800 East

July-Oct. 2000 — utility relocation.

Sept.-Dec. 2000 — construction of pavement, curb, gutter and sidewalks.

Feb.-March 2001 — pavement resurfacing.

Dec. 2000-Aug. 2001 — track installation, operating systems.

800 East-1100 East

Nov. 2000-Jan. 2001 — utility relocation.

Feb.-Sept. 2001 — construction of pavement, curb, gutter and sidewalks.

Jan.-May 2001 — pavement resurfacing.

March-Oct. 2001 — track installation, operating systems.

1100 East-Rice-Eccles Stadium

Oct. 2000-Feb. 2001 — utility relocation.

Jan.-May 2001 — construction of pavement, curb, gutter and sidewalks.

June-Sept. 2001 — pavement resurfacing.

May-Aug. 2001 — track installation, operating systems.

View Comments

Rice-Eccles Stadium Parking Lot

Sept.-Oct. 2001 — utility relocation.

March-April 2001 — construction of pavement, curb, gutter and sidewalks.

March-August 2001 — track installation, operating systems.