E Center
Ice hockeyCapacity: 8,500
Readiness: 99 percent
Left to do: Temporary lighting to be added at Games time for broadcasters and tents and trailers for concessionaires.
Seven Peaks Ice Arena at Provo
Women's ice hockey
Capacity: 8,000
Readiness: 95 percent
Left to do: 6,000 temporary seats and temporary tents and trailers for concessionaires to be added at Games time.
Delta Center
Figure skating, short-track speed skating
Capacity: 10,784
Readiness: 99 percent
Left to do: Temporary tents and trailers for concessionaires to be added at Games time.
Oquirrh Park Oval
Speed skating, Ice sledge (Paralympics)
Capacity: 6,500
Readiness: 10 percent
Left to do: Design process being completed, construction of 250,000-square-foot building to begin in June, completion by fall of 2000.
Ice Sheet at Ogden
Curling
Capacity: 2,000
Readiness: 95 percent
Left to do: Some 400 to 500 temporary seats, as well as tents and trailers, will be added at Games time. Concrete floor yet to be built under ice surface.
Winter Sports Park
Bobsled, luge
Capacity: 14,000
Readiness: 75 percent
Left to do: Tracks complete, but construction to begin this summer on buildings at starting gate, scales, sled storage and maintenance facilities, scoreboard and shading over the track. Tents and trailers to be added at Games time.
Winter Sports Park
Ski jumping, Nordic combined
Capacity: 20,000
Readiness: 30 percent
Left to do: Continued work on 120 meter and 90 meter jumps, chairlift, judges tower, new access road from Kimball Junction and park-and-ride lot. Tents and trailers to be added at Games time.
Soldier Hollow
Biathlon, cross-country skiing, Nordic combined
Capacity: 20,000
Readiness: 10 percent
Left to do: 18 kilometer trail and new access road being added this summer, and snow-making equipment, a competition management building, parking lots, park-and-ride lots, maintenance roads, culinary water and sewer yet to be constructed. Tents and trailers to be added at Games time.
Park City Mountain Resort
Giant slalom, snowboarding
Capacity: 20,000
Readiness: 50 percent
Left to do: Re-grading race courses and construction of half-pipe facility and stadium. Temporary tents and trailers to be added at Games time.
Deer Valley Resort
Slalom, mogul freestyle skiing
Capacity: 16,000-18,000
Readiness: 60 percent
Left to do: Hill for aerials, finish area, stadium and minor work on slalom course. Temporary tents and trailers to be added at Games time.
Snowbasin
Downhill, Super G
Capacity: 30,000
Readiness: 85 percent
Left to do: Minor course "fine-tuning" and construction of new access road. Resort will also build new buildings, but these are not required for the Games. Temporary tents and trailers will be added at Games time.
Rice-Eccles Stadium
Opening/closing ceremonies
Capacity: 56,000
Readiness: 99 percent
Left to do: Add 6,000 temporary seats, sound and lighting for opening and closing ceremonies and construction of the cauldron for the Olympic flame.